Free Gantt Chart Template for Excel

Plan tasks, dependencies, dates, milestones, owners, hours, and progress in one polished Excel workbook—with automatic weekly timeline bars and a live project dashboard.

Download the Excel template Free .xlsx file
No signup required
XGantt Chart Template.xlsx
Customer Portal LaunchON TRACK
Tasks20
Progress9%
Hours676
Milestones7
TaskAug 2431Sep 7142128Oct 512
Confirm scope
User research
UX design
Build portal
Launch
DashboardGantt SetupTask ListWeekly GanttMilestones
Automatic Gantt timelineWeekly schedule bars update from task dates
Dependency trackingConnect tasks with predecessor IDs and sequencing notes
Milestones and dashboardMonitor progress, deadlines, hours, and schedule health

A ready-to-use Gantt chart template for Excel

This free Gantt chart template for Excel turns a task list into a clear weekly project schedule. If you are building the plan from scratch, the project plan template for Excel can help define the broader project structure first.

Enter your tasks, owners, dependencies, start dates, due dates, planned hours, and completion percentages. The workbook uses formulas and conditional formatting to generate the Gantt bars, separate completed progress from remaining duration, flag overdue work, and update the dashboard.

It is designed for project managers, operations teams, consultants, agencies, startups, and small businesses that need a practical Excel project schedule without starting from a blank spreadsheet.

Download the free Excel Gantt chart

Includes sample data, formulas, dropdowns, conditional formatting, dashboard charts, milestones, and six ready-to-use worksheets.

Download .xlsx

What is included in the Excel Gantt chart template?

Project dashboard

See weighted progress, total tasks, overdue work, planned hours, finish date, milestones, task status, and schedule health.

Structured task list

Manage IDs, phases, tasks, owners, predecessors, status, dates, duration, hours, completion, schedule flags, and notes.

Weekly Gantt chart

View 20 weeks of work with formula-driven bars for completed progress and remaining planned duration.

Milestone tracker

Track key decision, approval, release, and launch dates with owners, status, days remaining, and deadline flags.

Dependencies

Reference predecessor task IDs to make sequencing visible and identify work that cannot start yet.

Duration and deadline formulas

Calculate task duration, days remaining, overall progress, overdue status, and milestone timing automatically.

How to make a Gantt chart in Excel with the template

1

Set the project timeline

Open Gantt Setup and replace the sample project name, manager, start date, reporting date, and timeline settings.

2

Add phases and tasks

Use the Task List to enter your work breakdown, owners, task status, predecessors, start dates, due dates, hours, and completion. For a more formal hierarchy, start with a work breakdown structure template.

3

Check the weekly timeline

The Weekly Gantt sheet converts task dates into visual bars. Dark blue shows completed progress and light blue shows remaining planned work.

4

Enter major milestones

Add approvals, handoffs, releases, and the final launch date to the Milestones sheet so deadline risks remain visible.

5

Review the dashboard

Use the dashboard during weekly project reviews to monitor progress, overdue tasks, workload, milestone timing, and schedule health.

Gantt chart example: customer portal launch

The included sample project shows how discovery, design, development, testing, training, and launch work connect across the schedule.

IDPhaseTaskPredecessorDue DateProgress
1InitiationConfirm project scope—Aug 25, 2026100%
4DiscoveryRun user interviews2Sep 4, 202625%
8UX & DesignCreate high-fidelity designs7Sep 18, 20260%
12DevelopmentBuild portal dashboard9Oct 9, 20260%
20LaunchRelease customer portal18, 19Nov 13, 20260%

How the automatic Gantt chart formulas work

The calculations remain visible and editable so you can review the logic or adapt the workbook to your process.

Task durationDue Date − Start Date + 1
Days remainingDue Date − Reporting Date
Weighted progressSUM(% Complete × Planned Hours) ÷ Total Planned Hours
Completed barTimeline Week ≤ Calculated Progress Date
Planned barTimeline Week overlaps Start and Due Dates
Schedule flagDone, Overdue, Due Soon, or On Track

Popular Gantt chart template use cases

A simple weekly Gantt chart is useful whenever tasks must happen in a particular sequence or different workstreams overlap. For teams coordinating several schedules, the multiple project tracking template provides a portfolio-level view.

Software projectsRoadmaps, sprints, releases, testing, migration, and rollout plans.
Marketing campaignsContent, creative, approvals, media, events, and launch schedules.
Construction planningPhases, inspections, procurement, contractors, and handoffs.
Client projectsDiscovery, deliverables, review cycles, billing milestones, and delivery.
Product launchesResearch, design, build, readiness, enablement, and go-to-market work.
Operational changesProcess design, training, deployment, adoption, and stabilization.

Gantt chart planning best practices

Break each deliverable into tasks that have a clear owner and measurable finish condition.
Use dependencies to show sequencing, but avoid connecting tasks that can genuinely run in parallel.
Add milestones for decisions, approvals, releases, handoffs, and launch dates—not routine tasks.
Update completion percentages consistently so progress bars and the dashboard remain credible.
Review the critical sequence and schedule risks before committing to a final delivery date.

Excel Gantt chart vs. project management software

An Excel Gantt chart is a strong fit for one project, a small team, or a schedule owned by one person. Gantt project management software becomes more useful when many people need to update the plan or changes must flow automatically across dependencies.

Planning needExcel Gantt chartProject management software
Single project with one schedule ownerGood fitOptional
Several people updating tasksVersion conflicts can occurShared real-time updates
Dependencies and date changesDates require reviewConnected rescheduling
Comments, files, and notificationsStored separatelyConnected to tasks
Multiple-project reportingDifficult to consolidatePortfolio rollups
Resource workload and capacitySeparate planning requiredIntegrated scheduling

KolApp connects Gantt schedules with Kanban, grid, resource scheduling, dashboards, budgets, resources, and portfolio reporting when the spreadsheet becomes difficult to keep current.

A Gantt chart shows the schedule—but is the schedule resourced?

A Gantt chart can show when work should happen, but dates alone do not confirm that the assigned people have enough time to deliver it. A schedule can look perfectly sequenced while several tasks compete for the same person during the same week.

That is where resource scheduling differs from project scheduling. Project scheduling organizes the work and dependencies; resource scheduling compares those plans with actual availability, workload, time off, and capacity.

Before committing to major dates, use the resource capacity calculator or learn how to calculate team capacity for projects. For growing teams, project management software with resource scheduling can connect the Gantt plan directly to the people expected to deliver it.

Frequently asked questions

Is this Gantt chart template for Excel free?

Yes. The .xlsx workbook is free to download and includes six worksheets, sample data, formulas, dropdowns, conditional formatting, charts, milestones, and a weekly Gantt timeline.

Does Excel have a built-in Gantt chart template?

Excel does not have a dedicated Gantt chart type. Gantt charts are commonly created with a stacked bar chart or a timeline grid using formulas and conditional formatting. This workbook uses the timeline-grid approach.

How do I change the dates in the Gantt chart?

Change the task start and due dates in the Task List. The Weekly Gantt bars, duration calculations, deadline flags, milestones, and dashboard update from those values.

Can I track task dependencies in this Excel template?

Yes. Each task includes a predecessor field where you can reference the ID of a task that must be completed first. The field makes sequencing visible, while date changes remain under your control.

Can I use the Gantt chart template in Google Sheets?

You can upload the .xlsx file to Google Drive and open it with Google Sheets. Review formulas, charts, and conditional formatting after conversion because spreadsheet applications may display some features differently.

What is the difference between a Gantt chart and a project timeline?

A project timeline often shows major events or milestones. A Gantt chart adds task duration, overlap, sequencing, ownership, and progress, making it more useful for detailed schedule management.